In order to achieve sustainable improvements in its environmental performance, the web-fed offset printing company WKS Kraft Schlötes implements ISO 50001-compliant energy management. This involves continuously checking all processes for energy efficiency. These checks revealed that the water cooling system of the commercial printing press for brochure printing is an energy-intensive process. KSB won the contract to provide new pumps capable of achieving competitive energy and cost savings.
In order to achieve sustainable improvements in its environmental performance, the web-fed offset printing company WKS Kraft Schlötes implements ISO 50001-compliant energy management. This involves continuously checking all processes for energy efficiency. These checks revealed that the water cooling system of the commercial printing press for brochure printing is an energy-intensive process. KSB won the contract to provide new pumps capable of achieving competitive energy and cost savings.
The Project:
Pumps for a web-fed offset cooling water system
Radical changes in media consumption have exerted constant pressure on printing to become cheaper – while increasing in technical sophistication. If printing is to remain relevant in the age of digitalisation, it must be as cost-effective as possible. As web-fed offset printing presses become more powerful and complex, costs incurred during production-related downtime can increasingly spiral out of control. Against this challenging background, KSB was charged with finding an energy-efficient solution ensuring reliable operation.
The Customer:
WKS Kraft Schlötes
Kraft Schlötes GmbH in Wassenberg, North Rhine-Westphalia, is a web-fed offset printing company that produces large volumes of brochures and newspaper supplements. It belongs to the WKS Group – which with 660 employees is one of Europe’s leading web-fed offset companies.
The Challenge:
Energy-efficient pumps and minimised downtime
In addition to achieving energy savings of almost 50%, KSB had another challenge to face: Web-fed offset printing plants of this size work in multi-shift operation around the clock, seven days a week. Under these conditions it was clear that modification of the cooling system had to minimise downtime for the printing press and ensure that production losses remained marginal.
The Solution:
Analysis, planning and implementation from one source
In collaboration with ENGIE, the specialist for heat dissipation systems in the printing industry, KSB began by evaluating data from the old pumps. The pump manufacturer then developed an energy cost calculation and determined which technology could be used to achieve the desired energy savings in the future. KSB was able to submit an offer for the new i.Cool cooling system from ENGIE which listed the total outlay for the new cooling system including all energy costs.
In terms of technology, the engineers opted for energy-optimised Etabloc pumps from KSB offering super premium efficiency to IE 4. Furthermore, the PumpDrive 2 variable speed system in combination with the PumpMeter pump monitoring unit ensured demand-driven operation and maximum energy savings.
The next stage saw specialists from KSB and ENGIE develop a strategy for replacing the cooling complex without creating long downtimes. It was agreed that large sections should be prefabricated and kept ready during ongoing operations before being installed in comparatively short breaks.
ENGIE’s employees were trained by KSB to commission the Etabloc pumps after delivery without KSB supervision. Once again, the kind of well thought-out product package which KSB offers its customers and project partners proved its worth: KSB’s pumps can be configured and commissioned after only a short training period.
After the new cooling system had been in operation for one year, ENGIE collaborated with WKS Kraft Schlötes to verify the consumption figures. The energy savings predicted in the previously prepared extrapolation were indeed confirmed and – at more than 50% – were even higher than the projected forecast. For WKS, ENGIE and KSB, this was confirmation that their cooperation had got everything right, all the way from analysis to planning and implementation.
Data | Facts | Figures
Plant: Cooling water system for web-fed offset printing plant
End user: WKS Kraft Schlötes
Project data:
13 x Etabloc pumps with PumpDrive 2 and PumpMeter
Commissioning training of ENGIE employees by KSB
Used products
Etabloc
Einstufige Spiralgehäuseblockpumpe, mit Leistungen nach EN 733, mit auswechselbarer Wellenhülse und Spaltringen, mit motormontiertem Drehzahlregelsystem. Mit KSB SuPremE, einem magnetfreien Synchron-Reluktanzmotor (Ausnahme: Motorgrößen 0,55 kW / 0,75 kW mit 1500 min⁻¹ sind mit Permanentmagneten ausgeführt) der Effizienzklasse IE4/IE5 gemäß IEC TS 60034-30-2:2016, für den Betrieb am Drehzahlregelsystem Typ KSB PumpDrive 2 oder KSB PumpDrive 2 Eco ohne Rotorlagegeber. Befestigungspunkte entsprechend EN 50347, Hüllmaße gemäß DIN V 42673 (07-2011). ATEX-Ausführung erhältlich.
PumpDrive 2/PumpDrive 2 Eco
เครื่องแปลงความถี่แบบระบายความร้อนด้วยตัวเองที่มีโครงสร้างแบบโมดูลาร์ช่วยให้สามารถแปลงความเร็วของมอเตอร์แบบอะซิงโครนัสและแบบซิงโครนัสผ่านสัญญาณมาตรฐานแบบแอนะล็อก ฟิลด์บัส หรือหน่วยปฏิบัติการได้อย่างต่อเนื่อง เนื่องจาก PumpDrive ระบายความร้อนด้วยตัวเอง จึงสามารถประกอบมอเตอร์บนผนังหรือตู้ึควบคุมได้ ควบคุมปั๊มได้สูงสุด 6 ตัวโดยไม่ต้องใช้ตัวควบคุมเพิ่มเติม