SES System Efficiency Service at a chemical production site
5 min read

SES in chemical production: full performance, half the energy costs

In Germany, a global manufacturer of different chemical products operates a plant producing synthetic resins and synthetic resin dispersions. In 2022, experts from SES System Efficiency Service were commissioned to investigate the cooling water systems of the two production buildings to uncover potentials for optimisation and find ways of tapping into them.

In Germany, a global manufacturer of different chemical products operates a plant producing synthetic resins and synthetic resin dispersions. In 2022, experts from SES System Efficiency Service were commissioned to investigate the cooling water systems of the two production buildings to uncover potentials for optimisation and find ways of tapping into them.

Optimisation

The savings potentials uncovered by System Efficiency Service

The challenge:

A system comprising variable speed pumps and fixed speed pumps in two groups

The cooling water system's pump system to be investigated is divided into two groups of pumps that are connected with each other. Pump group 1 is made up of three pumps of the type Etanorm – two of them operated at fixed speed and one at variable speed. Pump group 2 is made up of two Etanorm pumps – one operated at fixed speed and one at variable speed. The pumps are fitted with drives of different sizes, ranging from 30 to 45 kW.
The SES System Efficiency Service experts were commissioned to analyse the system in depth and identify optimisation opportunities. 

First, the goals of the analysis were defined:

  • Analyse the overall system and identify the overall efficiency
  • Create pump characteristic curves incl. the current operating point/range
  • Check the power input incl. efficiency
  • Recommend actions for operation to be efficient and reliable in the future

The KSB experts conducted a number of measurements at different points, including inlet pressure and discharge pressure, speed, flow rates and other variables. The results revealed:

For normal operation of pump group 1:

  • The pumps' flow rate was between 0 and 465 m³/h.
  • Control pressure of the collecting line: 5 bar
  • The pressure at the hydraulic worst case fluctuates between 0.5 and 3.2 bar.

For normal operation of pump group 2:

  • Flow rate between 80 and 200 m³/h
  • Control pressure of the collecting line: 6 bar
  • The pressure at bad-value point fluctuates between 1 and 4.6 bar.

Also, some problems had occurred in the system: Pressure losses were caused by the check valves installed as they were too small. Some of the motors were running at their ratings limit.
And: Frequent pressure drops were observed, that can be linked to various causes, such as operating a mix of fixed speed and variable speed machinery.

Based on an electricity price of 0.15 €/kWh and the previous operating parameters, the energy costs amount to over € 125,000 per year. 
 

Fünf Etanorm-Pumpen, aufgeteilt in zwei Gruppen

Easy to recognise: on the left, pump group 1 with 2 Etanorm pumps;  on the right, pump group 2 with 3 Etanorm pumps.

The solution:

Upgrading the system and using new, variable speed motors

KSB's experts prepared the following optimisation concept for the customer:

  • Increasing the pipe diameter between pump and collecting line to DN 150 
  • Replacing the current swing check valves and changing their installation position 
  • Using pumps with impellers of maximum impeller diameter
  • Using new motors with frequency inverters of at least 45 kW for three of the five pumps
  • KSB's engineered pump control system incl. frequency inverter, PLC with KSB software module for optimum pump operation 


Measurements in the control cabinet

Performance measurements in the control cabinet

The result:

An efficient and reliable system with reduced CO₂ emissions

The customer decided to implement the suggested measures and now benefits from the following:

  • In single-pump or dual-pump operation all operating points of PG 1 are covered in an energy-efficient manner.
  • A higher pressure is available in the system, and one pump is always on standby.
  • All operating points of PG 2 can now be covered by a single pump.
  • Speed control enables operation over the entire system curve. 
  • A higher pressure is available in the system, and one pump is always on standby.
  • In conclusion: higher system availability at constant pressure for all consumers
  • Significant reduction of life cycle costs
  • Massive energy savings equalling close to 50 %
  • Marked reduction of CO₂ emissions (almost 150 tons per year)
  • Plus a clearly enhanced operating reliability

Energy savings compared to current operation: almost 50 % equalling € 59,100 per year

Figures I Data I Facts

Application: Chemical industry

Project year: 2021

Scope: Investigating the pump system for cooling water supply

Prior to
optimisation

After optimisation

Energy consumption [kWh/a]1,2

835,500

441,500

Energy costs [€/a]1,2

125,300

66,200

Cost savings [€/a]2

59,100

Savings potential [%]2

47.2

CO₂ emissions [t/a]1,2

306

162

Reduction of CO₂ emissions [t/a]2

144

Payback period [a] 

1.7 years (PG 1)
0.8 years (PG 2)

1 Based on an energy purchase price of 0.15 €/kWh 

2 Production buildings 1 and 2 together

Services involved

SES System Efficiency Service

Pumps that are not optimally matched to the system consume too much energy. Thanks to SES System Efficiency Service from KSB, this doesn’t have to be the case.

  • Energy efficiency analysis
  • Damage analysis
SES System Efficiency Service

More articles on this topic

Don’t hesitate to contact us.

Would you like further information on KSB? Or have you got any questions surrounding our pumps, valves, services and spare parts? Just contact us. We would love to talk to you.